Certified Supplier Quality Professional (CSQP) Practice Exam

Disable ads (and more) with a membership for a one time $2.99 payment

Question: 1 / 135

During a post-project review, which of the following factors primarily measures project success or failure?

Were reasonable feedback tools utilized for top management?

Were slack times used efficiently?

Were the specified goals and objectives achieved?

During a post-project review, measuring whether the specified goals and objectives were achieved is a key factor in determining the project's success or failure. This directly assesses the project's ability to meet its intended outcomes and deliverables. Option A is not directly related to project success or failure but rather to feedback tools. Option B discusses the use of slack times, which is not a primary measure of project success. Option D focuses on resource utilization, which is important but not as critical as achieving the project's goals and objectives.

Were minimum expected resources utilized?

Next

Report this question